Sheraton Project Progress Update - March 3, 2008
Click on any thumbnail below to view a larger image.
|
| |
| |
Hotel Building 1 - 129 rooms
- TCO Received on 2/20/08
- All Rooms Occupied Last Week
- Final Punch List Items Continue
Hotel Building 2 - 121 rooms
- All Drywall Finishes Completed
- 3rd Floor Wallcovering Completed
- 2nd Floor Wallcovering Underway
- 1st Floor Ready for Wallcovering
- Tile Work Done, Vanities to Start Next Week
- West Side Exteriors 80% Completed
- East Side Exteriors 50% Completed
- Ready to Open 5/1/08
Lobby, Restaurant, and Conference Center
- TCO Received on 2/20/08
- Coffee Bar & Marketplace In Business
- Restaurant & Bar In Business
- Spa In Business
- Final Punch List Items Continue
Sheraton Carlsbad Resort & Spa Sitework
- Wedding Venue Area Completed
- Pool & Spa In-Use
- Path to Legoland Completed
- Hotel 2 Parking Lot Lighting Continues
- Access Road Lighting 75% Completed
- Event Venue Area Design Completed
|
 |
|
|
|
| |
|
| |
|
| |
|
| |
|
| |